This Monday, April 14, 2025, Phase 4 of the Malmok beautification project will officially begin.
The project will mainly involve:
• Marking the parking spaces
• Creating a brick-paved walking path
• Installing lighting alongside the walking path
• Planting more greenery
• Building a bus stop
This project is funded by the Tourism Product Enhancement Fund (TPEF).
Main contractor: Van Kessel Havenbouw N.V. (VKH)
The project will last 60 working days and is projected to be completed by July 10, 2025.
Work will start this Monday with the benches along the main road. Everyone is kindly asked to take the ongoing project into account.